Expansion of the THERMAL POWER STATION OF THE ŚRODA SUGAR FACTORY
Description of the investment:
Pfeifer & Langen Polska SA is the owner of 4 sugar factories in Poland. The company is a manufacturer of white sugar, cane sugar and a wide range of sugars.
Under the contract, INTROL expanded the thermal power stations of the sugar factory in Środa Wielkopolska, installing an ORm-30 boiler and Tp6/4 turbine transferred from other sugar factories along with the whole infrastructure.
Scope of work:
• transport of the ORm30 boiler from the Sugar Factory in Góra Śląska to the Środa Sugar Factory
• transport of the TP6/4 turbine set from the Witaszyce Sugar Factory to the Środa Sugar Factory
• disassembly of the heat exchangers station
• building permit design in order to obtain construction permit
• detailed designs of the turbine room building expansion
• delivery of the pressure components for the Orm30 boiler
• delivery of the boiler dust extraction and collection system
• delivery of the steam collector and fresh steam, supply water and back-pressure steam pipeline components
• delivery of complete dust removal and collection systems
• delivery of complete Control and Measurement Equipment and Automation for the Orm30 system and electrical system for the TP6/4 turbine set
• installation of the boiler along with the dust removal system
• removal of the steam collector
• installation of the fresh steam pipeline from the boiler to the collector and from the collector to the turbine along with the performance of compliance assessment at the Technical Inspection Authority CERT and granting CE marking
• installation of the feedwater pipelines
• extension of the gantry track in the engine room and exchanger room
• expansion of the turbine room building
• installation of the heat exchangers station along with piping
• installation of a complete TP6/4 turbine set
• installation of the back-pressure steam pipeline
• boiler start-up and test run performance
• start-up of the heat exchangers station
• fresh steam pipeline blowing
• TP6/4 turbine set tests, its start-up and test run performance
• operator training
Project type | Boilers |
Period | 2008 |
Client | Pfeifer & Langen Polska SA |